Water Main Replacement

Forest Green Blvd. - Water Main Replacement

Project Overview:

Capital improvement project for the City of Puyallup. Forest Green Boulevard Water Main Replacement consisted of multiple bid schedules / phases including but not limited to the replacement of approximately (2,839+996) 3,835LF of 4-inch, 8-inch, and 12-inch diameter water main and associated valving, hydrants, services, connections, and roadway restoration.

Project highlights:

This 65 working day project was substantially completed in just over 45 days, physically completed 10 days early and under initial project budget.